V2 Multi-Datacenter Replication Reference: Scheduling Fullsync
Deprecation Warning
v2 Multi-Datacenter Replication is deprecated and will be removed in a future version. Please use v3 instead.
Scheduling Fullsync Operation
With the pause
and resume
commands it is possible to limit the
fullsync operation to off-peak times. First, disable fullsync_interval
and set fullsync_on_connect
to false
. Then, using cron or something
similar, execute the commands below at the start of the sync window.
In these examples, the commands are combined in a .sh
or analogous
file:
#!/bin/sh
## Resume from where we left off
riak-repl resume-fullsync
## Start fullsync if nothing is running
riak-repl start-fullsync
At the end of the sync window:
#!/bin/sh
## Stop fullsync until start of next sync window
riak-repl pause-fullsync